We are using a request queue to do long-range planning, and have custom fields Quarter Start and Quarter End. Would like to have these default to specific dates (Q1 start = January 1, for example) so that we can see these items on a gantt chart. I can't figure out how to add logic to that or have it default. Thanks for the help!
Views
Replies
Total Likes
You can add the custom form to a project template and in the template you should be able to provide those values so that when you open a project with that template it will have those values in those fields in the live project
Views
Replies
Total Likes
I think this would end up being three fields. Your initial field where you pick Q1, Q2, Q3 or Q4. Then two calculated fields that are set to a date format, for Quarter Start and Quarter End, with the logic set to display the date based on what is selected in the initial field.
Thanks, this makes sense...I will try this!