Expand my Community achievements bar.

Join us LIVE in San Francisco on November 14th for Experience Makers The Skill Exchange. Don't miss out on this free learning event!
SOLVED

Calculated Field Help: Add task fields to a Project Form

Avatar

Community Advisor

I'm having a mental lapse, is there a way to put a calculated field on the project level that adds all the values on a task-level form?

1 Accepted Solution

Avatar

Correct answer by
Community Advisor

My default is no because I have not been able to accomplish this myself. However, I'm going to follow and hope someone proves us wrong. 




View solution in original post

3 Replies

Avatar

Community Advisor

I'm pretty sure you can't reference collections in a calculated field, so going to go with a big "no" on this one. Sorry!

Avatar

Level 2

Row Groupings:

Project >> Name Task >> Name

(Filtered by tasks that Can Start)

Column Groupings:

Parent >> Name

(the equivalent of our Milestones)

and I set the Matrix settings to Show Value Column it works for a report

Someone posted this to another similar question

I would double-check https://experienceleague.adobe.com/docs/workfront/using/basics/work-with-custom-forms/add-a-custom-f...

Task should be able to be manipulated to work in a project. There has to be a way with parent objects. Just a thought.

Avatar

Correct answer by
Community Advisor

My default is no because I have not been able to accomplish this myself. However, I'm going to follow and hope someone proves us wrong.