per this previous post, you can only reference objects that are on the References tab in the API explorer.
https://experienceleaguecommunities.adobe.com/t5/workfront-questions/reference-a-custom-field-from-another-object-in-a-calculated/m-p/552410
I think it's always been that way, as far as I know. "Fresh" queue details start out with 0 but if you ever put a number in there, you can't ever get back to the zero state. The obvious workaround would be to create a fresh queue. I'll bring up again that one of the best practices I can recommend is...
hey Matt, so this question you have here is turning out to be pretty much identical to your other question (found here: https://experienceleaguecommunities.adobe.com/t5/workfront-questions/viewing-calculated-issue-filed-gt-gt-converted-project-gt-gt/td-p/753070 ).
I'll give you a quick and general...
From my previous response, you hopefully picked up that I am not clear what you mean by the "request team", and it'll be difficult to answer any additional questions based on the initial ambiguity.
I can separately address your calculated field question -- did you catch my response to a different ...
This is not how validation logic works, so I've split this out into a separate question. If you have the right contract with Adobe, there is a feature called Business Rules which might be more in line with this. The link for this is:
https://experienceleague.adobe.com/en/docs/workfront/using/adminis...
One possibility is the project sharing or access setting. I'll show it in the sharing dropdown (screenshot) but you can also find this in the access section when you edit the project.
In this screenshot I show how I have shared a project with a team using "contribute" access, and then clicked on t...
I'm not clear on where you are stashing this "travel time" task, but as long as it is not in the same project, you might want to look into filtering hour types and see if it would work for you. See this link:
https://experienceleague.adobe.com/en/docs/workfront/using/manage-work/projects/manage-proj...
did you do this step I mentioned in a more recent post?
https://experienceleaguecommunities.adobe.com/t5/workfront-questions/reporting-on-task-completion/td-p/753566
You can do this by creating a User report. Go to filters, and select the license = ___ for your filter. Select each option one at a time (Standard, light, contributor), and then convert to text mode after each, to see what letter represents each.