@LouisaMf a few things to look at:
Schedule Mode on the project
Task constraint
Task duration
Task predecessors
e.g. if the Schedule Mode is "Start Date" and the project's planned start date is sometime in 2024, with a constraint of as soon as possible, a duration of 2, and no predecessors, your t...