Pittsburgh area Workfront Admins - BNY is hiring an Adobe Workfront Lead, Vice President, 4 days a week in office.
Adobe Workfront Lead, Vice President
Note: I don't work for BNY, so the above is all I know about the position. It was shared with me, so I'm sharing with all of you.
I can't imagine why they think a toggle to sort in the user's preferred order isn't needed, that's an option on most every other widget. If they're going to insist that it show oldest first then there should be an easy (one click) way for the project owner to indicate that approval is no longer need...
@YukselUy
I don't believe this is natively possible, but you might look into @Doug_Den_Hoed__AtAppStore's reply here: Can you change the start day of the work Week
Same here. Always happy to help or just chat Workfront and Fusion, heather.kulbacki@avalerahealth.com (or heather.kulbacki@icloud.com) and LinkedIn https://www.linkedin.com/in/heatherkulbacki/
If anyone stumbles across this later, I've receive a reply from support.
"After consulting with our resources, it appears that the only current solution to address the issue is by adding a second rate to the billing rate."
However, current documentation doesn't specify that this is needed for non-US...
Curious how many of you have non-USD projects AND use billing rates...? If you do, you might want to look into an issue that we've found. I've submitted a ticket, but still waiting on a response.
We discovered that on non-USD projects, the billing rate associated with a job role multiplied by the pl...
@ab751 I would go with these filters. The first one will give you tasks you're assigned to, then the OR and the second set will give you just your personal tasks