Hi @lalitc72210912
You can achieve this result by changing your metric settings to "Interpret zeros as no value", which will hide the line visualization if you want to have a date range that goes into the future.
However, some things to consider:
- Data for current day will change each time a user views the workspace, you could fix this with either a segment or calculated metric if this wasn't acceptable (i.e. exclude current day).
- If any data points in the historical data were zero, this would also mean the line visualization would not display (e.g. same as dates in the future).
Example