Project Budgeting and Resource Pools Our IT PMO is launching a process for IT project budget management and reporting using Workfront. This includes labor hours, labor cost, and expense, as well as budget, plan, and actual for each. Each IT role has been set with an hourly rate.We had been using one large companywide resource pool, and teams have been using Planner to manage resources - availability, planned, and actual hours. Having only one large companywide resource pool presented a couple challenges. First, when entering a resource labor budget within the Resource Budgeting section of the Business Case, a long list of companywide roles was listed, making it very unwieldy for a project manager to enter budgeted hours. Having only 3 months to enter data didn't help. This would require a lot of scrolling and page turning. Second, only IT roles have rates. Adding a budget to a role that doesn't have a rate would translate to $0. Therefore, it was advantageous to creat