workfront home screen - tasks due / complete

Avatar

Level 4

Is there any reason why the tasks on the workfront home screen show 0 due, when I know I have some due.

 

Where is this information being pulled from? 

1 Accepted Solution

Avatar

Correct answer by
Community Advisor

It's only going to pull items that had/have a planned completion date for this week. If the dates fall outside that range then it doesn't count them.

 

 




View solution in original post

2 Replies

Avatar

Correct answer by
Community Advisor

It's only going to pull items that had/have a planned completion date for this week. If the dates fall outside that range then it doesn't count them.

 

 




Avatar

Community Advisor

As @KellieGardner mentioned it’s only showing your week. See the top of your screenshot where you see My Week. You can change timeframe there. @Jaxelle 

If this helped you, please mark correct to help others : )