Is there any reason why the tasks on the workfront home screen show 0 due, when I know I have some due.
Where is this information being pulled from?
Solved! Go to Solution.
Views
Replies
Total Likes
It's only going to pull items that had/have a planned completion date for this week. If the dates fall outside that range then it doesn't count them.
It's only going to pull items that had/have a planned completion date for this week. If the dates fall outside that range then it doesn't count them.
As @KellieGWAB mentioned it’s only showing your week. See the top of your screenshot where you see My Week. You can change timeframe there. @Jaxelle
Views
Replies
Total Likes
Views
Likes
Replies