Is there any reason why the tasks on the workfront home screen show 0 due, when I know I have some due.

 

Where is this information being pulled from? 

This post is no longer active and is closed to new replies. Need help? Start a new post to ask your question.
Best answer by KellieGardner

It's only going to pull items that had/have a planned completion date for this week. If the dates fall outside that range then it doesn't count them.

 

 

1 reply

KellieGardner
Community Advisor
KellieGardnerCommunity AdvisorAccepted solution
Community Advisor
August 24, 2023

It's only going to pull items that had/have a planned completion date for this week. If the dates fall outside that range then it doesn't count them.

 

 

Madalyn_Destafney
Community Advisor
Community Advisor
August 24, 2023

As @kelliegardner mentioned it’s only showing your week. See the top of your screenshot where you see My Week. You can change timeframe there. @jaxelle 

If this helped you, please mark correct to help others : )