Expand my Community achievements bar.

Why would my due dates be different on two projects with the same start date, task constraints, and duration type?

Avatar

Level 3
 
Topics

Topics help categorize Community content and increase your ability to discover relevant content.

3 Replies

Avatar

Level 2

‚Check the Project Owners and the project settings to see if you have incorporated Weekends / Holidays in the set up.

Avatar

Level 4

It is possible that an assignee is on holiday, as registered in the Workfront calendar, and that therefore the planned end date of the task has been pushed further.

Avatar

Level 4

The above two comments are true and also IF the planned hours and/or planned start TIME isn't the same on all on both project or the tasks within them, it could throw off the planned completion date.