In the New Experience, I can't bulk edit Planned Hours on tasks. When multiple tasks are selected, the Planned Hours field is grayed out and only shows "multiple values" with no way to edit.

Support indicated there is a Duration Type selection that will open up the Planned Hours for editing, but I'm not seeing that field. The Old Experience makes this straightforward and doesn't require an additional selection.

For now, we're switching back to the Old Experience to manage this, but I'm curious if this will be addressed as the New Experience becomes the standard. Has anyone else run into this issue?