Expand my Community achievements bar.

When a work item is added to an iteration: Question on functionality. Do the Planned dates "stick"

Avatar

Level 3

I have used this functionality for some projects added to a Sprint (editing the Agile Pod). I turned in on for a project, completed the project schedule, and then added to a Sprint. I then changed the setting back to " Modify .. Date to match iteration start and end dates." It appears that the planned completion dates for the project did not not stick; I'm thinking that this changed overnight and it looks like the planned dates changed to the Sprint dates. What's the expected functionality?

0694X00000J4Ss9QAF.png

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

0 Replies