활동이 없어 이 대화는 잠겼습니다. 새 게시물을 작성해 주세요.
활동이 없어 이 대화는 잠겼습니다. 새 게시물을 작성해 주세요.
Hello,
I've got this dilemma... There is a project plan created for managing the process itself for processing hundreds/thousands of assets from Step 1 to Step N. After those steps are complete, we need to have a reporting mechanism to inform the team that X number of assets have been processed and completed. Have you had a similar case in your company? Please share your approach.
For example, there are 1000 widgets. For widget 1-100, we execute Step 1 thru Step N and complete the processing (creating, updating, uploading, approving, deleting, etc.) of those 100 widgets. Then, we need to track that 100 out of 1000 widgets have been completed, e.g. 10%. A report on a dashboard need to display that 10%. The challenge here is...instead of using an excel file with 1000 lines, how can we do this tracking in Workfront? Of course, we can layout the process from Step 1 thru Step N in Workfront as a series of tasks. However, it doesn't make sense to do it 1000 times.
Any idea on how to approach this asset completion tracking challenge? Thank you.
Best,
+Pavlin
토픽은 커뮤니티 콘텐츠를 분류하여 관련성 있는 콘텐츠를 찾는 데 도움이 됩니다.
interesting one Pavlin,
If it suits your requirements, I’d suggest several components:
This approach allows appropriate granularity to track each Batch independently and accurately, ensures the Batch Units are only “counted” once all child Step 1-N tasks are complete, thereby presenting accurate Batch % at both the Project and Task levels, minimizes the repetition of the Step 1-N tasks per project, but still allows for extra steps / issues, Batch Unit adjustments, etc.
And (personal preference) it also lends itself to charting and/or fancier logic to illustrate work in progress, or % complete of Batch math (eg 100 units all done step 4 of 5 could be counted as 100*80% complete = “80 units”...in theory).
Thanks for the puzzle: keep me posted on what you end up getting going!
Regards,
Doug
조회 수
답글
좋아요 수
Hi Doug, Thank you for the idea. I can definitely use it in my case. Ultimately, my real scenario is much more complicated but your solution can be used as a foundation of calculating sub-total and total amount(s) as we move along through the project. Thank you.
조회 수
답글
좋아요 수
My pleasure Pavlin,
Second only to "your solution is exactly what we need", hearing someone can use my idea without anything further from me is my favorite response. 😉
Regards,
Doug
조회 수
답글
좋아요 수