Expand my Community achievements bar.

SOLVED

how to create a report View average completion times for different types of tasks

Avatar

Level 2

hello everyone,

 I need to  create a kind of report where i can view the average completion times of different types of task  and how to show or highlight those with excessive times.

 

Thanks a lot

Hugo

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

1 Accepted Solution

Avatar

Correct answer by
Community Advisor

Hi there,

If you have a task report capturing the tasks you're looking for in your filters, you can have a column for task > actual duration. Click on that duration column, then Advanced Options in the upper right, and you can select Average.

Screenshot 2024-11-18 at 1.43.55 PM.png

Then in your grouping, you can group by project type or task type if you have custom fields delineating this (or if not, can group by project template if you're template names give an indication of type). Collapse the grouping. Then you can save and see the avg durations in the groupings of by type (whatever type means for you).

Note this is pulling actual duration, so if users are not good at marking tasks complete you may want to use planned duration. You could add some conditional formatting to the duration column if you wanted so show any avg duration exceeding X days shows as red, for example.

If this helped you, please mark correct to help others : )

View solution in original post

3 Replies

Avatar

Correct answer by
Community Advisor

Hi there,

If you have a task report capturing the tasks you're looking for in your filters, you can have a column for task > actual duration. Click on that duration column, then Advanced Options in the upper right, and you can select Average.

Screenshot 2024-11-18 at 1.43.55 PM.png

Then in your grouping, you can group by project type or task type if you have custom fields delineating this (or if not, can group by project template if you're template names give an indication of type). Collapse the grouping. Then you can save and see the avg durations in the groupings of by type (whatever type means for you).

Note this is pulling actual duration, so if users are not good at marking tasks complete you may want to use planned duration. You could add some conditional formatting to the duration column if you wanted so show any avg duration exceeding X days shows as red, for example.

If this helped you, please mark correct to help others : )

Avatar

Level 2

thank you so much. I was applying different filters,  I re built my report and was successful. just in case we could help others 

Captura de pantalla 2024-11-19 a las 5.08.52 p.m..png

Avatar

Community Advisor

That’s great!

If this helped you, please mark correct to help others : )