Show actual duration of completed projects in a project report
Hello! I'm trying to create a project report that shows actual duration of projects. One column is pulling the template duration, but I also want to show in a separate column the duration the project ACTUALLY took. Taking the actual start date and add up the actual completion date and show what that duration is (keep in mind, we have our schedule set up not to include weekends and holidays so it's not as straightforward as adding the days between the two dates). This will then show me a comparison to what the project SHOULD have started vs when it did and then how long is actually took. Ultimately, I want to show two things: 1) are our templates set up accurately for the duration needed and 2) we are allocating enough time, but our projects are starting too late; therefore we're always late getting them done. Warning: I do not understand text mode well at all. HA!