Hi Community,
Please how to setup Allocations in %? so that I can allocate % to assigned resources to a task in Workfront? see screenshot for more detail
Thanks your contribution is appreciated.
Mesh
Solved! Go to Solution.
Views
Replies
Total Likes
Hi Community,
Please don't worry, I figured it out.
Thanks for your help.
Hi Community,
Please don't worry, I figured it out.
Thanks for your help.
Are you not able to click directly into those allocation cells where it shows 0? If not, try adding planned hours on the task first from the ‘regular’ view of the task in the project, then go into it again after it has planned hours on it and revise specific allocations.