How are Allocation Dates determined for Planned Revenue (Project (Financial Data) report) | Community
Skip to main content
Heather_Kulbacki
Community Advisor
Community Advisor
November 11, 2025
Solved

How are Allocation Dates determined for Planned Revenue (Project (Financial Data) report)

  • November 11, 2025
  • 1 reply
  • 99 views

I've seen this discussion: https://experienceleaguecommunities.adobe.com/t5/workfront-questions/project-finances-allocation-dat...

but it doesn't quite tell me how those dates are determined.

 

We have a Project (Financial Data) report where the planned completion date of the project is in March 2026, but the report is showing allocation dates stretching out through August 2026.

Best answer by Heather_Kulbacki

@doug_den_hoed__atappstore Saved the day - suggested recalculating timeline and financials.

That worked.

The timeline hadn't been changed since late September so that didn't occur to us.

1 reply

Heather_Kulbacki
Community Advisor
Heather_KulbackiCommunity AdvisorAuthorAccepted solution
Community Advisor
November 11, 2025

@doug_den_hoed__atappstore Saved the day - suggested recalculating timeline and financials.

That worked.

The timeline hadn't been changed since late September so that didn't occur to us.