I've seen this discussion: https://experienceleaguecommunities.adobe.com/t5/workfront-questions/project-finances-allocation-dat...
but it doesn't quite tell me how those dates are determined.
We have a Project (Financial Data) report where the planned completion date of the project is in March 2026, but the report is showing allocation dates stretching out through August 2026.
¡Resuelto! Ir a solución.
@Doug_Den_Hoed__AtAppStore Saved the day - suggested recalculating timeline and financials.
That worked.
The timeline hadn't been changed since late September so that didn't occur to us.
Ver la solución en mensaje original publicado