SOLVED

Resource Management: Will reducing Schedules from 8 to 6 hours negatively affect other areas of Workfront?

Avatar

Level 4

In support of Resource Management and Capacity Planning in we want to reduce the hours considered for an FTE to about 75 - 85% to avoid overloading our team and account from indirect activities. For simplicity lets say reduce from 8 to 6 direct hours per day. The FTE field in the user profile does not seem to do anything so we are considering changing our schedule in Setup to reflect 6 hour days. 

Question: What are the implications to other areas of Workfront? Will this affect project schedules/timelines or the resource tools (i.e. Planner and Balancer) in unintended or negative ways?

 

Update schedule from 8 to 6 hour days:

8hrvs6Hr.jpg

1 Accepted Solution

Avatar

Correct answer by
Community Advisor

Hi Matt,

 

Before making any changes to your schedules, I recommend that you take a look at the new "Work Time" functionality that will be released in early March that should solve this exact problem (it's available right now in preview to test too). . . .  With this new capability, you can specify how much of a users day is dedicated to project work. Take a look at the release notes here, there's also a short video explaining the functionality. 

 

The best thing to do is to test your changes (whether they be to schedules or the new "work time" field) in your preview environment to get an understanding of the impact they have before making the change in live. Updating schedules in particular can affect lots of different areas of Workfront, but the extent depends on how your Workfront instance is configured. More info on this can be found here.

 

I hope this helps!

 

Best Regards,

Rich. 

View solution in original post

7 Replies

Avatar

Correct answer by
Community Advisor

Hi Matt,

 

Before making any changes to your schedules, I recommend that you take a look at the new "Work Time" functionality that will be released in early March that should solve this exact problem (it's available right now in preview to test too). . . .  With this new capability, you can specify how much of a users day is dedicated to project work. Take a look at the release notes here, there's also a short video explaining the functionality. 

 

The best thing to do is to test your changes (whether they be to schedules or the new "work time" field) in your preview environment to get an understanding of the impact they have before making the change in live. Updating schedules in particular can affect lots of different areas of Workfront, but the extent depends on how your Workfront instance is configured. More info on this can be found here.

 

I hope this helps!

 

Best Regards,

Rich. 

Avatar

Level 4

Work Time looks like it is exactly what I need. I didn't see that was coming. Thanks again!

Avatar

Community Advisor

I agree with Richard. We tried fiddling with the schedules so that our users could only be assigned 6 hours of work per day, but that started messing with our project timelines. If all your users are on the same schedule, you can use the "FTE" field at .75 to get your 6 hour days. But if you have users on different schedules the FTE option is disabled. The new "Work Time" field should fix that.

I'm still not clear on how "Work Time" interacts with "FTE" if all the users are on the default schedule though. Perhaps some can chime in and explain it.

Avatar

Level 4

Thanks, Randy. That was my concern too (messing with our project timelines). I'll have a play with the new functionality. Users in our group all use the same schedule but from what I can tell the FTE setting ignores time off etc. That seems less than useful.

Avatar

Community Advisor

The FTE setting ignores time off but the Workload Balancer honours time-off, and I believe that's the goal, right?

Make sure you have the right setting for FTE activation here>

Screenshot 2023-02-22 at 12.18.31 pm.jpg

Avatar

Level 4

Yes, that's the goal. I want to be able to plan to n% of a users time based on a FTE less than 8.