Hour report for Parent task and Child Task

Avatar

Level 10

Hi,
I created an Hours Report to collect hours from different projects and users. However, the report is not capturing all hours from the parent tasks. I need it to include hours registered in both child tasks and parent tasks, since many users log their time directly to parent tasks. Could you help me identify what might be missing in this report?

Kundanism_0-1757660200226.png

 

Looking for your expertise and suggestion. 

Regards

 

1 Reply

Avatar

Community Advisor

I'd try not using the timesheet ID filter in your screenshot. If you're wanting all hours from XYZ users I'd use Owner > Name instead. If you want from only specific users from specific projects, add an AND filter to use Owner > Name and Project > Name.

If this helped you, please mark correct to help others : )