I'm trying to run an hourly report and I'd like to know the milestone that the task is assigned to in the report. I can't seem to pull anything but the actual parent task. Anyone have any tricks, ideas, suggestions?
Topics help categorize Community content and increase your ability to discover relevant content.
Views
Replies
Total Likes
Hi Christina -
Are you saying you want the Milestone Name that is associated with the Parent task? Can you give me some more details?
What object are you building the report on? Sounds like Hours
This textmode code pulls the name of the milestone into an Hours report.
displayname=
linkedname=task
namekey=view.relatedcolumn
namekeyargkey.0=task
namekeyargkey.1=milestone
namekeyargkey.2=name
querysort=task:milestone:name
textmode=true
valuefield=task:milestone:name
valueformat=HTML
If there are other variables that I'm not accounting for let me know.
Hope this helps,
Teale
Views
Replies
Total Likes
Yes, this is an hours report.
Parent task: Production & Distribution (also the milestone name)
Subtask 1
Subtask 2
Subtask 3
What I'd like to know is for Subtask1......what's the milestone of the parent task? (Production & Distribution)
I'm not sure how to accomplish that since the subtask does not have a milestone associated with it.
Views
Replies
Total Likes
Maybe consider a different approach. Try using a Task report and filter where Actual Hours are greater than 0??
When I run the Hours report I see the same tasks over and over which is a lot of minutia to sift through.
On a Task report, this textmode pulls the milestone name of the parent task.
valuefield=parent:milestone:name
link.linkproperty.0.name=ID
link.linkproperty.0.valueformat=int
link.linkproperty.0.valuefield=parent:milestone:name
link.valuefield=parent:objCode
link.lookup=link.view
link.valueformat=val
descriptionkey=Milestone
textmode=true
shortview=false
stretch=0
linkedname=milestone
valueformat=HTML
namekey=parent
displayname=Milestone Name
width=150
querysort=parent:milestone:name
listsort=nested(parent).string(milestone)
In the screenshot, you can see the Task, it's Parent, the Milestone Name associated with the parent and the Actual Hours.
I'm not sure this is really helpful. I'm not able to find a way to access the parent tasks from Hours in the API Explorer. That's when I try to get creative.
Best -
Teale
Views
Replies
Total Likes
Hmm let me chew on that one for a bit. We're using an hour report since we have hours on projects, tasks, and requests so it was the most comprehensive one I could capture all time with. (we also want to pull in non-project hours like Meetings-Consultation, etc.).
I like the way you think....I'm going to keep on plugging at it!