Proof Approval Report: Group by Priority

Avatar

Level 2

Hello Workfront Community,

 

I would like to ask if there is a way to group by Project Priority in a Proof Approval Report?

 

I appreciate your help and opinions. Thank you.

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

1 Accepted Solution

Avatar

Correct answer by
Community Advisor

Hi @Ryzan99 - This should work, but let me know if not:

group.0.enumclass=com.attask.common.constants.TimelinePriorityEnum
group.0.enumtype=PROJ
group.0.linkedname=direct
group.0.namekey=priority
group.0.type=enum
group.0.valuefield=documentVersion:document:project:priority
group.0.valueformat=val
textmode=true

 

How I got this: I created a priority grouping in a project report and then added "documentVersion:document:project:" before priority in the valuefield line (which tells Workfront to retrieve project information)

View solution in original post

3 Replies

Avatar

Correct answer by
Community Advisor

Hi @Ryzan99 - This should work, but let me know if not:

group.0.enumclass=com.attask.common.constants.TimelinePriorityEnum
group.0.enumtype=PROJ
group.0.linkedname=direct
group.0.namekey=priority
group.0.type=enum
group.0.valuefield=documentVersion:document:project:priority
group.0.valueformat=val
textmode=true

 

How I got this: I created a priority grouping in a project report and then added "documentVersion:document:project:" before priority in the valuefield line (which tells Workfront to retrieve project information)