Project Template view showing planned hours for specific roles?

Avatar

Level 7
Is there a way to get a column view added that shows planned hours for a specific job role in the Project Templates tab? I want to see how many hours the Designers job role is allocated for each template so that I can batch apply a custom form based on those hours. I am not savvy enough in text mode to figure it out. Any advice? Leah Janz Metro Transit
1 Reply

Avatar

Level 10
Hi Leah, Try grouping by Job Role. Just make sure in your view settings you also have selected to 'Sum' the Planned Hours column. That way when you use the Grouping and View in combination you will see the total planned hours per Job Role. Hope that helps. Regards, David Cornwell