Project percent calculation - global setting

Avatar

Level 1
We have 2 types of projects – ones that are done in house, where it makes sense to base the project percentage on the hours worked – and ones that are done by external contractors, where it makes sense to base the project percentage on the duration. Trouble is this is a global setting in Workfront Has anyone found a way to get around this so it can be changed per project ? Thanks Adrian Lyndon DE Electronics Section Manager "https://www.ametek-land.com/"> Office: +44 (0)1246 581427 Address: AMETEK Land, Stubley Lane, Dronfield Derbyshire, S18 1DJ England E-mail: mailto:adrian.lyndon@ametek.com | Web: "https://www.ametek-land.com/"> https://www.ametek-land.com "https://www.ametek-land.com/contactus/keepinguptodate">
Topics

Topics help categorize Community content and increase your ability to discover relevant content.

1 Reply

Avatar

Level 3

Hello Adrian,

Currently there is not a way to use both of these settings for Percentage, it will need to be one or the other.