We create a task called "Project Oversight" for our project managers to record non-task time with the following details:
Task duration is equal to the project duration.
"Simple" allocation of 10% of total allocated hours on the project which gives us a general picture of capacity.
Task predecessor set to FF of the last task (or last group of parent tasks) to ensure if project tasks push out, so does our oversight task.