When creating a new story for an Agile Team, what dictates the list of available Parent Projects? I ask this question because I can only view a portion of the projects whether I am involved with the project or not. It does not show a full list of all projects.
Topics

Topics help categorize Community content and increase your ability to discover relevant content.

2 Replies

Avatar

Level 10
I believe an Agile Team needs to be assigned to tasks on the project, for it to appear.

Avatar

Level 10
Hi Cheron, The project needs to be in a Current status (or a custom status that equates to Current). If the project is in Planning, you cannot use it as a Parent Project when adding stories to your back log. Thanks