Hi Ian, I've used that approach and it worked very well:
you can create a temporary filter where (for example) "WBS" (Work Breakdown Structure) "contains 5.1" to quickly restrict to the subset of tasks of interest at that time
you can also create a temporary filter based on Indent (e.g. Indent = 0, Indent < 2, Indent < 3, etc) to quickly show only a certain depth of the subtasks
by using tasks, you can use predecessors to assign them; and note dependencies; and specify planned duration; and schedule them; and raise issues; and all the other task related goodness we've come to rely upon
you can also show the percent complete column and use it as an easily inline-edited and highly visual indicator of progress
similarly, you can use the percent completes at the parent levels and even the entire project to show testing progress
to repeat a battery of usecase tests, you can simply copy the project, reset the percent completes to zero, update the driving dates (I'd suggest ASAP otherwise so everything else just "adjusts")
So...yeah: apparently I'm a fan of this approach. Good to know. Regards, Doug Doug Den Hoed - AtAppStore