Hi Erika, Is the "Completion Mode" on the project set to automatic? If so, change it to manual and then try changing the percent complete of a task to 50. Also, if the task you're trying to adjust is a parent task, that won't work. You can only control the percent complete of tasks that have no children. Thanks, Narayan