Is it possible to retain cross-project predecessors if I create a copy of a project that has those cross-project predecessors already built in?

Avatar

Level 5

I am finding that when I create a copy of a project, those cross-project predecessors don't flow through to the copied project (but all other normal predecessors do copy over). Is there a setting where we can keep the cross-project predecessors as well?

Thank you!

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

2 Replies

Avatar

Community Advisor

Spoooooky Olivia,

None that I know of (having just looked again this week), so I just green-lighted an R&D project to develop that functionality for one of my clients this afternoon.

If you find out otherwise (or anyone else knows better), please let me know.

Regards,

Doug