Expand my Community achievements bar.

The Community Ideas review for H1 2025 is out now, see which ideas our Product team prioritized and let us know your thoughts.

Mark Solution

This conversation has been locked due to inactivity. Please create a new post.

Is it possible to retain cross-project predecessors if I create a copy of a project that has those cross-project predecessors already built in?

Avatar

Level 5

I am finding that when I create a copy of a project, those cross-project predecessors don't flow through to the copied project (but all other normal predecessors do copy over). Is there a setting where we can keep the cross-project predecessors as well?

Thank you!

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

2 Replies

Avatar

Community Advisor

Spoooooky Olivia,

None that I know of (having just looked again this week), so I just green-lighted an R&D project to develop that functionality for one of my clients this afternoon.

If you find out otherwise (or anyone else knows better), please let me know.

Regards,

Doug

Thanks Doug!