Esta conversa foi bloqueada devido à inatividade. Crie uma nova publicação.
Nível 1
Nível 2
Faça login na Comunidade
Faça logon para exibir todas as medalhas
 
     
     
    
            
          
Esta conversa foi bloqueada devido à inatividade. Crie uma nova publicação.
          
        
What I've done: created a report that finds the tasks to which I want to add a milestone. Then I select all of them and Edit, but the Milestone assignment in thge Settings section isn't an option. Is there another way to mass assign tasks to a milestone? Any clever workarounds?
Os tópicos ajudam a categorizar o conteúdo da comunidade e aumentam sua capacidade de descobrir conteúdo relevante.
           
        
I'm in the same boat. We just updated our milestone paths and it will be a very tedious and labor intense task for me to go into each project and select the new milestone tasks. Anyone have any tips?
Visualizações
respostas
Total de curtidas
          
        
Did you get a response on how to do this? I'm having the same issue.
Visualizações
respostas
Total de curtidas
          
        
Hi ladies -
Unfortunately you are correct. A way to bulk edit tasks to add a milestone name doesn't exist today. This is what I've done in the past as a workaround. Keep in mind this works because the team has a template with tasks that are named the same across the projects in their portfolio so I can filter on the portfolio and the task name.
Create a report that pulls a task that exists in multiple projects that you want to add a milestone name to
Include the Milestone Name field in the columns and then inline edit each one in the report - it goes quickly if you just start typing click enter to select the name and enter again to go to the next line item
Iterate on this for each different milestone name
It's not ideal but it works and doesn't take too long once you begin.
Hope this helps,
Teale
          
        
Visualizações
respostas
Total de curtidas
          
        
If you can't inline edit it typically means you don't have a milestone path associated with the project.
Visualizações
respostas
Total de curtidas
          
        
Or it's an access issue of being able to manage the task. Someone who understands permissions may be able to be more clear. Permissions get me every time.
Visualizações
respostas
Total de curtidas
          
        
Good point Jill!
Jen are you full admin in the system? If not, it could be a permissions issue.
Visualizações
respostas
Total de curtidas
          
        
Yes, I'm an admin and the milestone paths are assigned to the projects.
Visualizações
respostas
Total de curtidas
          
        
That's certainly odd. I'll let you know if anything else comes to mind.
Visualizações
respostas
Total de curtidas
          
        
Even if you are an admin, I’m pretty sure that if you don’t have the right permissions on the project or task you aren’t allowed to edit. I think. I’m an admin but I’m also on every single project as a resource manager so I always have access to everything, which is why permissions elude me, I don’t experience the problem too often. I would try adding yourself to a project and see if that changes the inline editing in the report.
Visualizações
respostas
Total de curtidas
          
        
Visualizações
respostas
Total de curtidas
           
        
I'm 100% sure that if you're the admin, it is not a permissions issue. Adding yourself as the resource manager to all projects is needed for resource planning views. Permissions to edit/manage a project come from two things:
1.) License: You need a Plan license to edit.
2.) Manage Access: If you're not the creator/owner of the project or report, you will need the owner to provide you with manage access.
System Administrator access trumps all of this, so you can edit projects and reports without a project/report owner to grant you manage access.
I no longer have to adjust anything because we did the labor for this already, but I did just run a report to see if I could inline edit. I ran into the issues Jen noted. Perhaps it the report type? I started with a Task report. Is that correct?
Visualizações
respostas
Total de curtidas
           
        
Found this thread attempting the same edit myself. I was able to use a Template Task report to mass update the Milestone Path on the template tasks, but nothing I do makes that same information editable in-line on a Task level report for existing projects.
The other thing I noted is that I had a difficult time getting the IDs associated with the path steps themselves. Usually I can just add a View to that resource and see it, but for this I had to build a Milestone report. It feels as if the milestone functionality isn't quite connected to tasks the way other information is, though I'm not sure that makes any sense.
That all being said, I am a determined person, and have thousands of tasks to retrofit with their information - so I finally designed a Fusion module to mass-update them all. Realize not everyone has that tool, but if you've found this thread and you do, reach out and I'll help you build the scenario.
Katherine
          
        
Well done Katherine,
Alternatively, for those without Fusion, our Excel Updater solution can set Task Milestone IDs, too.
Regards,
Doug
Visualizações
respostas
Total de curtidas
 
					
				
				
			
		
Visualizações
Curtida
respostas
Visualizações
Curtida
respostas