Hi,

has anyone know how the project's condition is calculated?

I found an article discussing this here but still wondering if there is like a granular level calculation.

2 Replies

Avatar

Community Advisor

That's pretty much it.

 

Basically if you have tasks that are showing behind, at risk or late that results in the dates of your projected or estimated completion dates out, then the project will go into at risk, behind, or late condition.