I want to create a task report that shoes the hours for each individual assigned to the same task. In my efforts to create this report, all of the hours are showing up under one person when the task actually includes 3 - 4 more individuals.
Topics help categorize Community content and increase your ability to discover relevant content.
Views
Replies
Total Likes
I have this column added to one of my views to see hours by Assignee
displayname=Assignment Breakdown
listdelimiter=<br>
listmethod=nested(assignments).lists
textmode=true
type=iterate
valueexpression=CONCAT({assignedTo}.{name}," (",{role}.{name},") - ",{workRequired}/60,IF({workRequired}/60>ABS(1)," Hours"," Hour"))
valueformat=HTML
Hope that helps
Hi @Anthony Imgrund‚
Thanks and I remember you helped the above code to make our lives easier.
As suggested, we started to use assignment breakdown as column in project view, the code is;
displayname=Assignment Breakdown
listdelimiter=<br>
listmethod=nested(assignments).lists
textmode=true
type=iterate
valueexpression=CONCAT({assignedTo}.{name}," (",{role}.{name},") - ",{workRequired}/60,IF({workRequired}/60>ABS(1)," Hours"," Hour"))
valueformat=HTML
Id planned hours is 40 hrs equally between 3 assigments, then the planned hour shows 13.3333333 hrs each.
Any solution to round this number?????
Thanks in advance.
Mvh
Kundan
Views
Replies
Total Likes
Huge help. Thanks so much Anthony!
-Rick