I won't get into details around why it's needed but we are looking to do a calculated field in a task view that would show us the % complete Workfront thinks a task should be at. For these projects we use Planned Hours to calculate our % Complete
Ideally it would look similar to this
Name | Duration | Pln Hrs | Planned Start Date | Planned Completion Date | % Complete (native Workfront field that currently exists and allows updates) | Calculated field to show what % should be |
Task 1 | 10 days | 40 Hours | xx | xx | 30.00% | 50% |
Task 2 | 100 days | 50 Hours | xx | xx | 25.00% | 75% |
Task 3 | 5 Days | 5 Hours | xx | xx | 10.00% | 5% |
Solved! Go to Solution.
Views
Replies
Total Likes
I finally stumbled upon an answer in the community https://experienceleaguecommunities.adobe.com/t5/workfront-questions/attempting-to-calculate-quot-ex...
displayname=Expected % Complete
textmode=true
valueexpression=IF({plannedStartDate}<$$TODAY,IF(ROUND(((WEEKDAYDIFF({plannedStartDate},$$TODAY)+1)/(WEEKDAYDIFF({plannedStartDate},{plannedCompletionDate})+1)*100),2)>100,"100%",CONCAT(ROUND(((WEEKDAYDIFF({plannedStartDate},$$TODAY)+1)/(WEEKDAYDIFF({plannedStartDate},{plannedCompletionDate})+1)*100),2),"%")),"0%")
valueformat=HTML
Hi @KellieGWAB - Is the below what you're looking for? It's the % of Planned Hours / Actual Hours. I wasn't fully clear on what the calculation criteria was here, so let me know if not!
displayname=Custom % Complete
textmode=true
valueexpression=DIV({workRequired},{actualWorkRequired})
valueformat=asPercent
Views
Replies
Total Likes
@VictoriaLinn - so the calculation is tricky in my mind so I probably didn't do a good job explaining. And it's Monday.
What we are hoping to see is what the percent complete should be on each task. So not based on any actual work that's happened but a calculation of how much work (percentage wise) should have taken place by now.
Hopefully that makes more sense.
Thanks,
Kellie
Views
Replies
Total Likes
@KellieGWAB how would you want to go about determining what that %complete should be?
Is a matter of (task 1, for example), the planned start date was 5 days ago in a 10 day duration task, so we should be 50% done by now? Workfront will divide your 40 hours evenly over those 10 days, so I don't think you need to consider hours in there.
For that, have you tried something along this line: ($$TODAY-plannedStartDate)/duration
Or is there some other expectation for what the %complete should be?
Views
Replies
Total Likes
Thanks Heather. This is exactly what I came up with while I was sleeping last night, dreaming about Workfront calculations and it got be partially there.
Views
Replies
Total Likes
LOL It's so great to know I'm not the only one who dreams in Workfront!
Views
Replies
Total Likes
I finally stumbled upon an answer in the community https://experienceleaguecommunities.adobe.com/t5/workfront-questions/attempting-to-calculate-quot-ex...
displayname=Expected % Complete
textmode=true
valueexpression=IF({plannedStartDate}<$$TODAY,IF(ROUND(((WEEKDAYDIFF({plannedStartDate},$$TODAY)+1)/(WEEKDAYDIFF({plannedStartDate},{plannedCompletionDate})+1)*100),2)>100,"100%",CONCAT(ROUND(((WEEKDAYDIFF({plannedStartDate},$$TODAY)+1)/(WEEKDAYDIFF({plannedStartDate},{plannedCompletionDate})+1)*100),2),"%")),"0%")
valueformat=HTML