Expandir minha barra de realizações na Comunidade.

Submissions are now open for the 2026 Adobe Experience Maker Awards.

Mark Solution

Esta conversa foi bloqueada devido à inatividade. Crie uma nova publicação.

SOLUCIONADO

Custom Form attached to Task

Avatar

Level 3

Hi,

 

I have a custom form that is attached to a Task. Is there a way to set it up that the task can only be marked as completed when the custom form has been filled out?

 

Wibke

1 Solução aceita

Avatar

Resposta correta de
Community Advisor

 

Hi @WibkeKu,

 

To my knowledge, there is no connection between custom data and the status of (in this case) the Task to which it is connected that would prevent users from closing the task without first ensuring the custom data is complete.

 

As a workaround, I sometimes add a calculated parameter to validate the form (e.g. IF(ISBLANK(DE:Field A),0,1) + IF(ISBLANK(DE:Field B),0,1)) so that I can then use it for row formatting (e.g. in this simple example, blue if 0, yellow if 1, green if 2) and/or filtering (e.g. show all Tasks where Actual Completion Date is not blank, but the calc is < 2) so I can then "educate" those (Last Updated By) users who are closing them without first checking.

 

Regards,

Doug

Ver solução na publicação original

3 Respostas

Avatar

Resposta correta de
Community Advisor

 

Hi @WibkeKu,

 

To my knowledge, there is no connection between custom data and the status of (in this case) the Task to which it is connected that would prevent users from closing the task without first ensuring the custom data is complete.

 

As a workaround, I sometimes add a calculated parameter to validate the form (e.g. IF(ISBLANK(DE:Field A),0,1) + IF(ISBLANK(DE:Field B),0,1)) so that I can then use it for row formatting (e.g. in this simple example, blue if 0, yellow if 1, green if 2) and/or filtering (e.g. show all Tasks where Actual Completion Date is not blank, but the calc is < 2) so I can then "educate" those (Last Updated By) users who are closing them without first checking.

 

Regards,

Doug

Avatar

Community Advisor

You could also just check if a required field in the form is filled out, and if not, mark the task as "new" or some form of "not done". Also maybe post a note to the task explaining that they need to fill out the form or the task will keep coming back to life. This won't prevent the task from being marked complete but it will mark it "not done" within a few minutes.

Avatar

Community Advisor

@WibkeKu - As the others said, unfortunately this isn't possible. As a possible solution, we often use approvals so the task/issue/project will route to someone to verify the information is accurate and then once approved the object would be marked complete. This could potentially be a solution if you have someone who could be the verifier. Good Luck.