Okay, I'm guessing this is a collections thing. But I've been working on something else and I got side-swiped with a reporting request that I'm working through now.
I'm looking to create a Project report which utilizes three calculated fields. The first two fields display the actualCompletionDate of two tasks with two different milestones applied. The third is a calculation of WEEKDAYDIFF between those two dates.
So, the first question: Is this even possible, and Help?
I've tried doing something like this...but it's not working:
IF({milestoneID}="5851d120007a5a899272acf155310bda",CONCAT({plannedCompletionDate}),CONCAT(" "))
I'm guessing it's "Collections And Output To Excel Time" but I'd prefer to keep everything within WF. Help?
-j