Task name: First Day - Start date is entered as due date
Task name: Monday Prior to Start date - pulls due date from first day and sets as prior Monday.
Going off of this article and using 19fs-12w as predecessor.
https://experienceleague.adobe.com/docs/workfront/using/manage-work/tasks/use-task-predecessors/lag-...
This does work, but only if First Day - Start Date lands on a Monday.
For example: Start date is 6/26, Monday Prior will update to 6/19. But if Start date is 6/28, Monday Prior updates to 6/26. Is it possible to set this up so it will always pull previous week Monday and not just previous Monday?
Thank you in advance!!