    Thank you for the reply! I should have mentioned, I have not assigned the tasks yet (because, yes, a user's schedule can cause this problem).    Also, it is the first two tasks in the timeline and their constraints are ASAP, so this is not an earlier task's constraint causing this.   The specific pr...

    Typ

    Diskussionen

    Zugriffe

    1.7K

    Likes

    0

    Antworten

    3
  •  in Workfront Discussions 05.01.23
    I am planning a new project: the Project Planned Start date/time is Jan 3 at 8am. The default schedule is 8am-5pm. The first task is 1-day duration: its planned start time is 8am however it's planned completion time is 4pm?? Why isn't is planned to complete at 5pm?  This is causing the second task t...