Hi All - Does your organization have a rule of thumb in regards to the optimal number of days (Duration) that a Task should span as compared to its Planned Hours? For instance: if a Task's Planned Hours = 4 Hours or less, then the Duration = 1 Day. If a Task's Planned Hours is between 5 and 8 hours,...