How do I enable the ability to see and adjust the Last execution date of the incremental query? - I have a need to see the records from the last time the workflow ran, so I want clear out the last execution date of my incremental query. According to the documentation, I should be able to do this after the workflow runs for the first time on the Scheduler activity.
From
"After the first execution of the workflow, you can see in this tab the last execution date that will be used for the next execution. It is automatically updated every time the workflow is executed. You still have the possibility to override this value by manually entering a new one so that it fits your needs."
However, I am not seeing the last execution date after the workflow runs:
Instead, I am still just seeing this:
How do I enable the ability to see and adjust the Last execution date of the incremental query?
Thanks,
Julia
Solved! Go to Solution.
Views
Replies
Total Likes
Hi, this issue has cropped up post release 21.2 and support should be already aware, fix is not yet available for this.
Hi, this issue has cropped up post release 21.2 and support should be already aware, fix is not yet available for this.
Views
Replies
Total Likes
It's indeed currently not shown in the dialog.
Though if you have admin permissions, you can go to the App Setting => Options and search for lastExec to see the timestamp.
Views
Replies
Total Likes
Views
Replies
Total Likes
The name contains Workflow ID + Activity Name.
What you can do to find it out:
Views
Replies
Total Likes
Views
Replies
Total Likes
Views
Likes
Replies