Hi @lalitc72210912
You can achieve this result by changing your metric settings to "Interpret zeros as no value", which will hide the line visualization if you want to have a date range that goes into the future.
However, some things to consider:
- Data for current day will change each time a user views the workspace, you could fix this with either a segment or calculated metric if this wasn't acceptable (i.e. exclude current day).
- If any data points in the historical data were zero, this would also mean the line visualization would not display (e.g. same as dates in the future).
Example
![Jacob_T1_0-1611708265466.png Jacob_T1_0-1611708265466.png](https://experienceleaguecommunities.adobe.com/t5/image/serverpage/image-id/29403iA1C13E7B766B9870/image-size/medium/is-moderation-mode/true?v=v2&px=400)
![Jacob_T1_3-1611708540642.png Jacob_T1_3-1611708540642.png](https://experienceleaguecommunities.adobe.com/t5/image/serverpage/image-id/29406i191CA937359869A9/image-size/medium/is-moderation-mode/true?v=v2&px=400)
![Jacob_T1_2-1611708279650.png Jacob_T1_2-1611708279650.png](https://experienceleaguecommunities.adobe.com/t5/image/serverpage/image-id/29405iAC4DC9DF6FD85079/image-size/medium/is-moderation-mode/true?v=v2&px=400)