Why is Can Start = False?

Avatar

Community Advisor

Before I ping support, I thought I would throw this out to the community. I have two tasks in a project with predecessors that have been met, but the Can Start value is False. Why? Is there something hinky going on with that cross-project predecessor?

Screenshot 2025-04-07 at 2.02.59 PM.png

Topics

Topics help categorize Community content and increase your ability to discover relevant content.

1 Accepted Solution

Avatar

Correct answer by
Community Advisor

No need to apologize!

While preparing my new summary for you, though, I found the culprit: One of the child tasks under task 6 had open issues. This fact was hidden to me because we rely a fair amount on the Percent Complete field, which apparently we can set to 100% and the status will remain In Progress. As a result of this revelation, I have posted an idea for folks to upvote: Disallow 100% Percent Complete if there are open i... - Adobe Experience League Community - 748142

View solution in original post

8 Replies

Avatar

Community Advisor

 

Hi @Lyndsy-Denk,

 

Does Recalculate Timeline resolve it?

 

Regards,

Doug

Avatar

Community Advisor

Nope. I tried that several times.

Avatar

Level 4

Have you checked the Task Constraint?

Avatar

Community Advisor

Both tasks are set to As Soon As Possible.

Avatar

Community Advisor

Update: I busted my theory that the issue is with the cross-project predecessor. When I removed all predecessors in the problematic tasks, Can Start flipped to True. So I was able to narrow it down the culprit to predecessor 6, which is a parent task. All child tasks under 6 are complete. One child task has a constraint of Start No Earlier Than, but when I changed it to Must Start On or even As Soon As Possible, Can Start still said False.

Avatar

Community Advisor

I'm so sorry, can you start over with your explanation? And maybe include a screenshot that shows task 6? I'm just wondering what the status, and maybe other specifics of task 6 is (you've said it's a parent, you've said all children are complete, but you haven't specified if the parent is complete). Also, has this ever worked or are you trying something new and can't get it working?

Avatar

Correct answer by
Community Advisor

No need to apologize!

While preparing my new summary for you, though, I found the culprit: One of the child tasks under task 6 had open issues. This fact was hidden to me because we rely a fair amount on the Percent Complete field, which apparently we can set to 100% and the status will remain In Progress. As a result of this revelation, I have posted an idea for folks to upvote: Disallow 100% Percent Complete if there are open i... - Adobe Experience League Community - 748142

Avatar

Community Advisor

 

Well spotted @Lyndsy-Denk,

 

That tracks, and is As Designed, but...yeah.

 

Regards,

Doug