Expand my Community achievements bar.

The Community Ideas review for H1 2025 is out now, see which ideas our Product team prioritized and let us know your thoughts.
SOLVED

Request to Project Conversion Metrics

Avatar

Level 2

Has anyone created a cycle time report for the amount of time it takes from request to project conversion?

1 Accepted Solution

Avatar

Correct answer by
Level 4

Hi,

 

You should be able to do this at the project level with DATEDIFF, both in a report or a calculated field:
ROUND(DATEDIFF({entryDate},{convertedOpTaskEntryDate}),2)

View solution in original post

2 Replies

Avatar

Correct answer by
Level 4

Hi,

 

You should be able to do this at the project level with DATEDIFF, both in a report or a calculated field:
ROUND(DATEDIFF({entryDate},{convertedOpTaskEntryDate}),2)

Avatar

Level 2

Thank you!