One of our users created a report to calculate the date 23 days after the date field "Vendor due date" by using
valueexpression=ADDWEEKDAYS({project}.{DE:Vendor due date},23). It has been working fine but calculated one value that was a weekend. Any ideas on what could be going wrong? Thanks in advance! Madison Schanbacher Ferguson Enterprises, Inc.