Yeah, it's kind of personal preference. However, everyone should know that if you leave X as the Planned Completion Date and Y as the Actual Completion Date, the problem becomes that your Predecessor (really Successor) Tasks are still calculated off the Planned Completion Date. So if Task A finished 2 weeks late, and Task B is a successor task it is still using the old Planned Completion Date and looks like it's starting on time, but it should be starting 2 weeks later. Cascade that through the rest of the project plan and you could be 2 weeks (or more) behind schedule and not know it because none of the Successor tasks are moving. Hope that makes sense. Vic Alejandro, PMP, CSM | IT | Sr. Technical Project Manager Denver Water | t: (303-628-7262) | c: (303-319-6473) "http://www.denverwater.org/">
http://www.denverwater.org INTEGRITY | VISION | PASSION | EXCELLENCE | RESPECT