Yeah Workfront does kinda consider a Task or Issue that has a Status of "Complete – Pending Approval" as a Complete Task or Issue. I noticed that with an Issue I changed to "Complete – Pending Approval" – I could no longer find the Issue in the Open Issues tab. It was in the Completed Issues tab, even though the Approval wasn't done yet. So based on that, I believe that's what's happening with your Task. Workfront is considering it Complete, even if the Approval isn't done yet and thus any successor tasks are now "Ready to Start" regardless of whether they're using FS, FF, SS, etc. I'm not saying it's right, but I believe that's what's happening. Vic Alejandro, PMP, CSM | IT | Sr. Technical Project Manager Denver Water | t: (303-628-7262) | c: (303-319-6473) "http://www.denverwater.org/">
http://www.denverwater.org INTEGRITY | VISION | PASSION | EXCELLENCE | RESPECT