Is there any way to log time for Saturday/Sunday in the timesheet but not have those days accounted for in the project timeline? Basically we are working weird hours due to the pandemic, but I don't want the project timeline to change because of those weird hours. Leah Janz Metro Transit
Hi Leah! I"ve checked on my own Projects and even though I"m set for "5 Typical Work Days a Week", I can log time on weekends. If this is something you cannot do, please submit a Support Case so we can take a better look at this with you!