Expand my Community achievements bar.

Join us LIVE in San Francisco on November 14th for Experience Makers The Skill Exchange. Don't miss out on this free learning event!
SOLVED

Template Duration vs. Project Duration rollup variance

Avatar

Level 2

Hi,

I am trying to do a variance between the template duration and the project actual duration. I have used the formula below and some others but nothing is working. This works on another report I have with a custom form field on a task vs. planned task work required.

 

displayname=Variance Plan vs Time Completed

textmode=true

valueexpression=SUB({template:durationMinutes},{actualDurationMinutes})

valueformat=compound#M:D

 

Thanks!

 

1 Accepted Solution

Avatar

Correct answer by
Level 1

Hi Nikki,

 

Try the below instead:

 

valueexpression=SUB({template}.{durationMinutes},{actualDurationMinutes})
textmode=true
valueformat=compound#M:D
displayname=Variance Plan vs Time Completed

There was an error in your syntax. "template" and "durationMinutes" need to be in separate curly brackets.

 

Best Regards,

Rich. 

View solution in original post

3 Replies

Avatar

Correct answer by
Level 1

Hi Nikki,

 

Try the below instead:

 

valueexpression=SUB({template}.{durationMinutes},{actualDurationMinutes})
textmode=true
valueformat=compound#M:D
displayname=Variance Plan vs Time Completed

There was an error in your syntax. "template" and "durationMinutes" need to be in separate curly brackets.

 

Best Regards,

Rich. 

Avatar

Level 2

Thank you so much! That worked! and I added minutesAsDaysString so now I have days difference. 

displayname=Variance Plan vs Time Completed
textmode=true
valueexpression=SUB({template}.{durationMinutes},{actualDurationMinutes})
valueformat=minutesAsDaysString

Avatar

Level 10

@Nikki_Clemmons 

Just curious, where did you used this text mode, is it in project view or template view as a column?

Thanks in advance.

Mvh

Kundan.