Expand my Community achievements bar.

SOLVED

Task List won't automatically update based on Predecessors

Avatar

Level 2

Hello,

 

Apologies as I'm sure this is something that shouldn't be so hard to fix but I I've tried searching for answers before submitting this question and I can't find the solution. 

 

I've inherited a bunch of old projects from a previous admin and the task lists were set up manually with no template. I need to copy a lot of the projects and then adjust the tasks to new dates. The task lists are very simply and straightforward.10 tasks total and the predecessors go down 1, 2, 3, etc. starting with task #2. The issue is when I select a new completion date and adjust the start/due date for task #1 - none of the following tasks update even though they all have predecessors set. 

 

Not sure what I am doing wrong here or what needs to change. 

1 Accepted Solution

Avatar

Correct answer by
Community Advisor

I would start with the task constraints and make sure they aren't set to a "must" constraint as that will dictate the dates essentially overriding the Workfront timeline. 




View solution in original post

2 Replies

Avatar

Correct answer by
Community Advisor

I would start with the task constraints and make sure they aren't set to a "must" constraint as that will dictate the dates essentially overriding the Workfront timeline. 




Avatar

Community Advisor

 

Hi @camostafin,

 

I concur with @KellieGardner and invite you to review this Task Constraints Primer in general, and this ASAP section in particular.

 

Regards,
Doug