Are there a "cliff notes" on how to get a tasks in a project to calculate planned start dates based on
- Project Start Date (Schedule Mode = Start Date)
- Task predicessors
- Assigned Resource Availability
- Planned Hours
In other words, I know:
- The tasks
- The planned hours for the task
- Who will work on the task
- The resources available hours per day (6 hours per day)
- Predicessors to the task
I want Workfront to tell me when each task can start and should end thus calculating the end date
I essentially want to use the assigned resource's availability as a constraint on the task.
As I read the info on Duration Types, Task Constraints and Predicessors I am getting lost in the possiblities and not finding anything that accounts for the resources 6 hour day.