Are there a "cliff notes" on how to get a tasks in a project to calculate planned start dates based on
In other words, I know:
I want Workfront to tell me when each task can start and should end thus calculating the end date
I essentially want to use the assigned resource's availability as a constraint on the task.
As I read the info on Duration Types, Task Constraints and Predicessors I am getting lost in the possiblities and not finding anything that accounts for the resources 6 hour day.
Views
Replies
Total Likes
Terri,
This link, https://experienceleague.adobe.com/en/docs/workfront/using/administration-and-setup/add-users/create... specifically the section around Resource Planning should be helpful. Since people are in meetings and not doing tasks full-time there are fields in the user profile area for FTE and Work Time to help set users in exactly the fashion your wanting below. Its not a cliff notes, sorry, there is a little reading to understand both fields intent.
Hey Kurt - thanks for the article. I am still stuck. For examples:
What am I missing?
Views
Replies
Total Likes
@TerriWi1 just checking in! Were you able to get this resolved? If one of the replies above helped—whether it completely solved the issue or simply pointed you in the right direction—marking it as accepted can make it much easier for others with the same question to find a solution. And if you found a different way to fix it, sharing your approach would be a great contribution to the community. Your follow-up not only helps close the loop but also ensures others benefit from your experience. Thanks so much for being part of the conversation!